You will need the following tools and hardware to install the Galaxy Power System:
· Material-handling equipment to unload the cabinet at the installation site, remove from shipping
container, and set in final position [minimum lifting capacity: 900 lbs. (410Kg)
Note: Use the equipment weights and dimensions as a guideline for choosing material-handling
equipment.
· Drill and drill bits to install floor anchors
· 3/16-inch (5mm) Allen-head wrench (provided)
· Insulated hand tools
· Screw drivers (flat-blade and Phillips)
· Wire cutters and stripper
· Torque wrenches (see Table 3-A) 35-513 in·lbs (4-58 N·m)
· Sockets:
Metric English Equivalent Hardware
8mm 5/16" M5
10mm -- M6
13mm 1/2" M8
17mm 11/16" M10
19mm 3/4" M12
-- 3/8" 1/4"
-- 9/16" 3/8"
· Crimp tools
22 - 16 gauge
10 - 500 MCM (5-120mm
2
)
· Jeweler’s screwdriver
· Digital multimeter (DMM) with 0.05% accuracy on dc scale
· Load box (200 amperes @ 48V)
· Laptop or personal computer (PC) loaded with Windows 3.1 or later (optional)
· ESD wrist strap*
*Equipment is ESD sensitive. It is required that an ESD wrist strap be worn during installation and
repair. An ESD wrist strap (408157105) is provided with each controller.
3. Getting Started

Table of Contents

Related product manuals