Millennium II Controller System Alarm Test
The Alarm Test provides a means of testing the operation of any or all of the system alarm relays and
their wiring to the connected alarm system. The test cannot be performed if any alarms are active. In
addition, Rectifier HVSD (High Voltage Shut Down) and RFA (Rectifier Fail Alarm) tests can be included.
For additional information, consult the Millennium Controller product manual.
Millennium II Controller System Alarm Test
Step Action
Connecting to Load
The system is ready to connect to equipment loads. Install or turn on load protectors when needed.