4.7 Installation with draw rod at site
4.7.1 Preparations at site
Overview
This procedure is only applicable if the lower draw rod with the bottom contact (36) is installed in the
transformer.
G004532
Procedure
1. Loosen the M8 bolts (24).
G004684
2.
Remove the M10 bolts (6), and then remove the
outer terminal (5).