Installation and commissioning guide
2750 515-1 EN, REV. 14, 2020-06-26
3. Install the lifting tool (1), the M10 bolts (6) and the
washers (7).
For GOE 250 to 950: align the side of the
lifting tool with the oil-level sight glasses (25).
For GOE 1050 to 2550: align the side of the
lifting tool with the oil-level guage (26).
G005056
Torque
40 ±4 Nm
4.
Put the pull-through cord (12) through the
box-spanner (13).
G004680
5.
Apply Molykote Multilube to the thread on the
pull-through cord (12), and then connect it to the
draw rod.
NOTE!
Or use a lubricant with equal properties
to Molykote Multilube.
G004686