Installation and commissioning guide
2750 515-1 EN, REV. 14, 2020-06-26
7.3 Re-packing of the bushing
Overview
G005004
Procedure
1. Put plastic wrap on the draw rod, and fix it to the transport box.
CAUTION!
Do not put the draw rod into the bushing, the threads on the draw rod will scratch the inside
of the center-tube.
2.
Put plastic wrap on the upper draw rod and the support tubes.
3.
Lift the bushing. Refer to Lifting the bushing out of the transport box, page 17.
4.
Lower the bushing into the transport box.
CAUTION!
Make sure that the there is soft bedding in the transport box.
CAUTION!
Make sure that the oil valves and test tap does not make contact with the transport box, or
other objects.
5.
Attach the bushing to the transport box in the same way as when it was delivered.
CAUTION!
Make sure that the bushing cannot move or rotate in the transport box.
6.
Close the transport box.
NOTE!
Refer to Lifting the transport box, page 16 and Transportation, page 15.
End of instruction

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB GOE Series and is the answer not in the manual?

ABB GOE Series Specifications

General IconGeneral
BrandABB
ModelGOE Series
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals