Installation and commissioning guide
2750 515-1 EN, REV. 14, 2020-06-26
8. Tighten the draw-rod nut (10).
NOTE!
Make sure that more than 10 mm of
the threads on the upper draw rod (35)
is remaining.
G006663
Torque
10 Nm
9.
Remove the pull-through cord (12).
10.
Remove the bolts (6), the washers (7) and the
lifting tool (1).
G004679
11.
Tighten the draw-rod nut, refer to Hydraulic tightening of the draw-rod nut, page 49, or Manual
tightening of the draw-rod nut, page 53.
End of instruction