34ANNEX
Before starting the system OK/ NOK
Execute the commissioning procedures specified by the batteries manufacturer
Start the system
(a)
While the system is running
(b)
Set the 'P setpoin
Check the current of the inverter
Check the power absorbed by the inverter
Check the batteries voltage through the BMS
Check the batteries current through the BMS
Set the 'P setpoint

Set the 'P setpoint
Check the current of the inverter
Check the power absorbed by the inverter
Check the batteries voltage through the BMS
Check the batteries current through the BMS
Set the 'P setpoint
Set up the user requirements for harmonics and reactive power/ balancing
Check the line currents (Irms, THDI and waveforms)
Check the line voltage (Vrms, THDV and waveforms)
9.4 Testing (with battery)
Remarks:
(a)

(b)

NOTE: During the load test with the batteries keep the monitoring of the batteries parameters to avoid any value be out of
proper range of operation.
Project:
PQstorI Issued by:
Commissioning report Date: 