Installation checklist 97
7
Installation checklist
Contents of this chapter
This chapter contains a list for checking the mechanical and electrical installation of the
inverter.
Checklist
Go through the checks below with another person. Obey the Safety instructions given on
the first pages of this manual.
Check that…
MECHANICAL INSTALLATION
There is sufficient free space around the unit. (See page 132.)
The ambient operating conditions are allowed. (See page 144.)
The unit is properly fastened to the floor and wall. (See Mechanical installation)
The cooling air is able to flow freely and cooling air volume is sufficient.
ELECTRICAL INSTALLATION (See Electrical installation)
The capacitors are reformed if stored over one year (refer to Capacitor reforming
instructions (3BFE64059629 [English]).
The inverter is grounded properly.
The AC line voltage matches the nominal output voltage of the inverter.