Rated Power | 100 kW |
---|---|
Max DC Voltage | 1100 V |
Number of MPPT | 6 |
Protection Rating | IP65 |
Operating Temperature Range | -25°C to +60°C |
Max AC Power | 100 kW |
Topology | Transformerless |
Cooling | Forced air |
AC Voltage Range | 400 V |
Frequency Range | 50/60 Hz |
Explains the meaning and usage of warning symbols in the manual for hazard communication.
Defines the permissible operational parameters and conditions for the MVCS unit.
Outlines essential safety instructions for performing installation, commissioning, and maintenance tasks on the MVCS.
Provides fundamental safety precautions to be followed before performing any work on the MVCS equipment.
Lists the minimum required safety equipment and guidelines for selecting PPE based on conditions.
Specifies critical safety procedures to follow before working within the MV switchgear and transformer sections.
Provides safety protocols for working on the auxiliary services board, including de-energization steps.
Presents safety instructions to be followed during the normal operation of the MVCS to prevent hazards.
Outlines critical safety instructions and procedures for safely lifting the MVCS unit.
Provides step-by-step instructions with figures on how to attach slings and connect to the lifting equipment.
Refers to general safety instructions and specific handling guidance for moving the MVCS.
Provides guidance on selecting a location and constructing a suitable foundation for the MVCS, considering local regulations.
Details the critical steps and checks required to safely lift and place the MVCS onto its foundation.
Explains the correct method for securely fastening the MVCS to the foundation using attachment brackets.
Outlines the process for constructing an earthing electrode and performing earthing according to local regulations.
Details the requirements for constructing an earthing electrode and connecting the MVCS to it.
Explains how internal PE terminals and frames are connected to busbars and how incoming cables are earthed.
Provides step-by-step instructions for connecting inverter power cables to the AC cabinet, including cable sizing and hole marking.
Details the process of connecting power grid cables to the MV switchgear, including cable termination and interface types.
Lists essential checks to ensure the MVCS installation is complete, correct, and safe before operation.
Details the sequence of tasks for safely starting up the MVCS, including pre-checks and connections.
Defines the recommended schedule for maintenance actions (I, P, R) based on years from start-up.
Outlines routine inspections and tasks to be performed at least every six months for preventive maintenance.