Finalizing the installation
Contents of this chapter
This chapter describes how to finalize and check the installation of the PVS-100/120 medium
voltage compact skid (MVCS). Obey all local regulations.
WARNING!
Only an authorized electrician is permitted to install the cabling to the MVCS. Obey
the Safety instructions (page 9), and the local safety regulations. If ignored,
physical injury or death may occur, or cause damage to the equipment.
WARNING!
Do not do electrical installation work during a thunderstorm.
WARNING!
Make sure that all external cable entries are fully sealed to prevent entry of foreign
elements, such as animals and insects.
Finalizing the installation
Clean the MVCS of all dirt.
Repair any damages to the paint surface. See section, Maintenance of painted
surfaces (page 57).
If not yet done, seal the cable entries, cover the cable entries with sand and sprinkle a
handful of cement over the sand. The cement hardens in a few days and it forms a
barrier against small animals and plant growth.
7
Finalizing the installation 47

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB PVS-100 Series and is the answer not in the manual?

ABB PVS-100 Series Specifications

General IconGeneral
BrandABB
ModelPVS-100 Series
CategoryInverter
LanguageEnglish

Related product manuals