Start-up and operation
Contents of this chapter
This chapter describes the start-up procedure of the PVS-100/120 medium voltage compact
skid (MVCS) and the general operation criteria.
WARNING!
Only an authorized electrician is permitted to install the cabling to the MVCS. Obey
the Safety instructions (page 9) and the local safety regulations. If ignored,
physical injury or death, or damage to the equipment may occur.
WARNING!
Do not do electrical installation work during a thunderstorm.
Tools needed
Voltage detector
Insulation resistance meter. For more information, see section Measuring the insulation
resistance of the cabling (page 42).
Personal protective equipment
Prerequisite
WARNING!
Use original silica gel bags only during transport. Install new silica gel bags for
storage.
1. Remove the transportation covers.