EasyManua.ls Logo

ABB ret650 - Page 122

ABB ret650
392 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Example for time coordination
Assume two substations A and B directly connected to each other via one line, as
shown in the Figure 47. Consider a fault located at another line from the station B.
The fault current to the overcurrent protection of IED B1 has a magnitude so that
the overcurrent protection will start and subsequently trip, and the overcurrent
protection of IED A1 must have a delayed operation in order to avoid
maloperation. The sequence of events during the fault can be described using a
time axis shown in Figure
47.
I> I>
A1 B1
Feeder
Time axis
t=0 t=t
2
t=t
3
The fault
occurs
B1 trips and
A1 starts
Breaker at
B1 opens
=IEC05000205=2=en=Original.vsd
Fault
t=t
4
Protection
A1 resets
t=t
1
B1 and A1
start
IEC05000205 V2 EN-US
Figure 47: Sequence of events during fault
where:
t=0 is when the fault occurs
t=t
1
is when protection IED B1 and protection IED A1 start
t=t
2
is when the trip signal from the overcurrent protection at IED B1 is sent to the circuit breaker.
t=t
3
is when the circuit breaker at IED B1 opens. The circuit breaker opening time is t
3
- t
2
t=t
4
is when the overcurrent protection at IED A1 resets. The protection resetting time is t
4
- t
3
.
To ensure that the overcurrent protection at IED A1 is selective to the overcurrent
protection at IED B1, the minimum time difference must be larger than the time t
3
.
There are uncertainties in the values of protection operation time, breaker opening
time and protection resetting time. Therefore a safety margin has to be included.
With normal values the needed time difference can be calculated according to
Equation
25.
Section 7 1MRK 504 169-UEN A
Current protection
116 Transformer protection RET650 2.2 IEC
Application manual

Table of Contents

Other manuals for ABB ret650

Related product manuals