20 | © 2019 ABB | 1SDH001000R0002 - ECN000109166 - Rev. D Management operations | 3 - Description
Continued from the previous page
8. Extract the disconnection crank from its housing See Figure 43.
9. Press the lock pushbutton and insert the crank in the moving part. In this phase the moving part is still
in DISCONNECT position. See Figure 44.
Figure 43
2
1
Figure 44
10. Turn the crank clockwise until the pushbutton comes out and the indicator shows that the circuit-
breaker is in TEST position. See Figure 45.
Figure 45
11. Press the lock button and rotate the crank clockwise until it comes out and the indicator shows that
the circuit-breaker is in CONNECT position. See Figure 46.
1
2
Figure 46
Continued on the next page