EasyManua.ls Logo

ABB TPL65-A10 - Page 56

ABB TPL65-A10
120 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Operation Manual / TPL65-A10 / -A30
5 Maintenance / 5.3 Cleaning the compressor during operation
© Copyright 2020 . All rights reserved. HZTL2482_EN Rev.E March 2020
5.3.1 Wet cleaning using external water-pressure vessel
(XC3)
Operating state prerequisites for wet cleaning XC3
NOTICE
To be able to carry out a satisfactory cleaning process which has been
tested and is recommended by ABB Turbocharging, the following pre-
requisites must be fulfilled:
u Engine load 50 … 85%
u Start of cleaning cycle in accordance with following description for
wet cleaning operation with XC3.
Operating procedure for compressor wet cleaning with XC3
Operating the water pres-
sure vessel
u The operating state prerequisites for compressor cleaning with XC3
must be fulfilled.
u Remove sealing plug (X).
u Fill vessel with required volume of clean water (see table Cleaning
parameters).
u Screw in sealing plug (X).
Page 54 / 117

Table of Contents

Related product manuals