ASSEMBLY OF THE SWITCHGEAR AT SITE 23
5/2 Section view
for figure 5/1
5/2
1500
>4000
2400
(78)
11
12
2565
7
(820)
(130)(130)
2
9
5 8
3 14
50
200
10
1732 650
300 2085
1000 35
1
2000
Ceiling
Circuit breaker
1) Minimum dimensions
1 Operator aisle
2 Inspection aisle
3 Opening for control cables (instead of individual openings,
continuous openings or drilled holes are possible)
5 Openings for power cables
7 Panel type UniGear ZS3.2 ...31.5 kA
8 Power cables
9 Projecting of floor frame: 5-12 mm above finished floor level
10 Conductor to main earthing bar
11 Screen 50 mm to 60 mm
12 Hight of the cable cellar, to be determined by the client
14 Guiding ramp, optional (recommended for circuit-breaker insertion)