MINIMUM OPERATIONAL SPACES
HANDLING
INSTALLATION OF THE UNIT
All the required operational spaces must be checked before starting
installation:
• renewal and expulsion air ducting position;
• passage of cables for power supply;
• proper maintenance and cleaning operations;
In particular:
• a space of at least 200 mm must be available at the condensation
drain to implement the siphon (more detailed instructions are found
on the label).
• there must be a space of at least 400 mm near the water coil
collectors to install the valve.
• There must be a space of at least 1000 mm for routine maintenance
(eye checks, replacing and cleaning lters).
PACKAGING
The TA series air conditioning units are generally supplied on pallets and
packed in cardboard boxes.
STORAGE ON SITE
The TA series units must be stored indoors.
TRANSPORT
Transport must be performed taking the following precautions:
• suitable blocking onto the lorry deck;
• load protection with adequate protection;
VERIFICATIONS UPON RECEPTION
On receipt of the unit, a visual control must be carried out to check that no
damage has occurred during transport. If damage has occurred it must be
highlighted on the accompanying transport document.
Follow the indications below to install the equipment correctly.
The completion of all operations, according to specic requirements, is left
to the experience of the installer.
The unit is supplied with support brackets to mount it on the wall or
ceiling.
The brackets can be mounted with the bends facing inwards or outwards.
For dierent types of assemblies, the following instructions must be
modied depending on specic worksite requirements.
It is always advised to x the brackets to the ceiling rst of all (with expan-
sion plugs or threaded tie rods) and then to x the units to the brackets.
When performing vertical installation, the screws fastening the brackets
will rest on the shorter part of the slots.
To fasten the unit to the wall, proceed as follows:
- mark the four holes for the expansion plugs;
- prepare the xing system (expansion plugs or tie rods);
- x the brackets to the wall or to the ceiling using nuts, washers
and back nuts;
- screw on the 4 side screws to the unit to the brackets;
- for horizontal installation, before tightening the screws, nuts and
back nuts make sure that condensation drains properly;
It is advised to provide a slight slope towards the drain to favour
runo.