OmniSwitch 6350 Hardware Users Guide September 2015 page 2-1
2 Getting Started
Installing the Hardware
Items Required
Grounding wrist strap
Phillips screwdriver
Flat-blade screwdriver
Site Preparation
Environmental Requirements
OmniSwitch 6450 switches have the following environmental and airflow requirements:
The installation site must maintain a temperature between 0° and 45° Celsius (32° and 113° Fahrenheit)
and not exceed 95 percent maximum humidity (non-condensing) at any time.
Be sure to allow adequate room for proper air ventilation at the front, back, and sides of the switch.
Refer to “Airflow Considerations” on page 2-3 for minimum clearance requirements. No clearance is
necessary at the top or bottom of the chassis.
Electrical Requirements
Note. Alcatel-Lucent switches must be installed by a professional installer. It is the responsibility of the
installer to ensure that proper grounding is available and that the installation meets applicable local and
national electrical codes.
OmniSwitch 6450 switches have the following general electrical requirements:
Each switch requires one grounded electrical outlet for the chassis power supply. OmniSwitch 6450
switches offer AC power supply support only. Refer to the following chapters for
more information.
Each supplied AC power cord is 2 meters (approx. 6.5 feet). Do not use extension cords.
Redundant AC Power. It is recommended that each AC outlet resides on a separate circuit. With
redundant AC, if a single circuit fails, the switch’s remaining power supplies (on separate circuits)
can remain operational.