Before starting the air powered screed, there are a few items that need to be looked over.
Make sure that bolts are secure and will not vibrate loose.
Check jam nuts on top pipe to ensure that they are tight against the top pipe coupler.
Check the hydraulic level in the tank for the hydraulic winches (if applicable).
Check winch cables to make sure that they will not loosen during the screed run.
Look over the forms to check for unevenness so that the screed will not hang up.
Ask yourselves these questions when preparing your screed for a job.
What is the “exact” pour width?
What is the slump?
Istheslabat,crowned,orinverted?
What is the required surface tolerance?
Choose screed type and size based on the above information.
Are any accessories required?
Do the winches work properly?