Filling and bleeding the system
Proceed as follows:
Fill and bleed the heating circuit
In addition, open the bleeding valve on the condens-
er of the heat pump. Bleed condenser
Insulating the hydraulic
connections
Insulate the vibration decouplers and the outside pipes
of the heating circuit so that they are sealed against va-
por diffusion.
NOTICE:
Insulate in accordance with applicable lo-
cal standards and directives.
CAUTION.
Install the outside pipes of the heating cir-
cuit beneath the frost line.
Proceed as follows:
Check seals of all hydraulic connections. Conduct
pressure test...
Insulate all connections and lines of the heat circuit
and the heat source.
Commissioning
DANGER!
Prior to commissioning the unit, the air
ow bafes must be mounted and the fac-
ing panels closed.
Proceed as follows:
Conduct a thorough installation inspection and go
through the items on the general checklist.
General checklist.
The installation inspection will prevent damage
to the heat pump system that could be caused by
incorrect installation work.
Make sure of the following…
Clockwise rotary eld of the load power
supply (compressor).
Installation and assembly of the heat pump
according to the information in this operating
manual.
All electric installation work must be properly
completed.
A 3-pole automatic circuit-breaker must
be installed for the compressor. It must have a
contact gap of at least 3 mm.
The heating circuit must be rinsed, lled and
thoroughly bled.
All valves and shut-off devices of the heating
circuit must be open.
All pipe systems and components of the system
must be sealed.
Carefully ll out and sign the completion report for
heat pump systems…
Completion report for heat pump systems.
In Germany and Austria:
Send completion report for heat pump systems
and general checklist to the manufacturers factory
customer service department.
In other countries:
Send completion report for heat pump systems
and general checklist to the manufacturer’s local
partner.
Overview “Customer service”.