Page #35 background image
Installation & Start-Up | 3-11
Electrical Connections Power Signal Junction Boxes
1. Access terminal in power signal Junction Box.
2. Connect the 4 to 20 mA analog output and alarm contacts from the ter-
minal block to user recording equipment.
3. Connect serial communication from analyzer to the PC being used for
customer parameter setup.
RS-232 Out - Connect RS-232 cable connector on the sample system plate.
RS-485 In - Connect RS-485 in cable to the terminal block.
OR
RS-485 Out - Termination plug is installed at the factory. Remove the RS-485
termination plug from the RS-485 Out connection when communicating
with multiple analyzers except for the last analyzer in a chain.
4. Connect line power to analyzer.
5. When installing external wiring to the junction box, use appropiate
thorough-wall bulkhead connections suitable for the hazaradous area
classiication and the environmental conditions encountered.
Analyzer Start-up
1. Turn on power source.
2. Open main process shut-off valve. Adjust sample pressure between 20
and 50 psig. Allow the analyzer to dry down before recording moisture
concentration measurements.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Ametek 3050-SLR and is the answer not in the manual?

Ametek 3050-SLR Specifications

General IconGeneral
BrandAmetek
Model3050-SLR
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals