Installation and Start-Up | 3-13
c. Apply a high-temperature thread lubricant to the threads of the (4)
M6 x 60 mm screws (300-8741, Figure 3-1), install the screws, and
tighten them to secure the Heater Assembly to the Sample Probe.
Refer to Chapter 5 for the 240 V version of the Heater Assembly.
The thread lubricant must not contain copper.
15. Complete the wiring, described under “Wiring Sample Probe Heaters
Controlled by Standalone Temperature Controller (Retrofits),” and
then return to this procedure.
16. Take all necessary safety precautions and apply power to the ana-
lyzer, described under “Powering Up the Probe Heater Assembly and
Analyzer,” and then return to this procedure.
17. Install the Insulating Jacket on the HAG Probe to allow it to warm up
quickly.
The procedure is complete.
!
CAUTION
NOTE

Table of Contents