External Service Platform Installation (Optional)
RefertoFigures 25through27onpages 17through19foryourunitplatformassembly.
1. Lifthang-onmodule(s)intoplacebyplacinghangerintonotchatthetopoftheunit,
andsecuretounitusing3/8”x11/4”bolts.SeeDetail A(Figures 25through 27).
2. Slideclampsbehindpanelangeatbottomofhang-onmodule(s)supports,andsecure
toplatform. SeeDetail B (Figures 25through 27).
3. Ifapplicable,liftdrop-inplatformsection(s)betweenmountedhang-onmodules,and
lowerintopositionsothatitrestsonsupportchannels.Boltplatformandrailingsinto
placeusing3/8”x11/4”bolts.See Detail C (Figures 26and 27).
Detail A
Detail B
Figure 25. External Service Platform Assembly
for 8’ x 6’ and 8’ x 9’ Units
Optional Accessories
Intake Sound Attenuation
Assembly (FXV Only)
External Service Platform
Installation
NOTES:
1. Platform can be installed prior
to rigging coil section for easier
installation.
2. Platforms, ladders and safety
cages can be added at the time
of order or as an aftermarket
item.
3. Safety gates are provided for all
handrail openings as standard.
All components are designed to
meet OSHA requirements.
Unit
3/8x11/4”Bolt
3/8”Flatwasher
Hang-onModule
Hang-OnModule
3/8”Rivnuts
Flange

Related product manuals