External Service Platform Installation (Optional)
RefertoFigures 25through27onpages 17through19foryourunitplatformassembly.
1. Lifthang-onmodule(s)intoplacebyplacinghangerintonotchatthetopoftheunit,
andsecuretounitusing3/8”x11/4”bolts.SeeDetail A(Figures 25through 27).
2. Slideclampsbehindpanelangeatbottomofhang-onmodule(s)supports,andsecure
toplatform. SeeDetail B (Figures 25through 27).
3. Ifapplicable,liftdrop-inplatformsection(s)betweenmountedhang-onmodules,and
lowerintopositionsothatitrestsonsupportchannels.Boltplatformandrailingsinto
placeusing3/8”x11/4”bolts.See Detail C (Figures 26and 27).
Detail A
Detail B
Figure 25. External Service Platform Assembly
for 8’ x 6’ and 8’ x 9’ Units
Optional Accessories
Intake Sound Attenuation
Assembly (FXV Only)
External Service Platform
Installation
NOTES:
1. Platform can be installed prior
to rigging coil section for easier
installation.
2. Platforms, ladders and safety
cages can be added at the time
of order or as an aftermarket
item.
3. Safety gates are provided for all
handrail openings as standard.
All components are designed to
meet OSHA requirements.
Unit
3/8x11/4”Bolt
3/8”Flatwasher
Hang-onModule
Hang-OnModule
3/8”Rivnuts
Flange