Section Assembly of Optional Three-Piece Cells
Table 2. Minimum Vertical Dimension and Spreader Bar Length for Optional Three-Piece Lift for Single Air Intake FXV and CXVB Units
Model Number Lower Section Plenum Section Coil Section
FXV CXVB H W1 W2 H W3 H W4
FXV-0806x-x-x CXVB-x-0806-x
3'-6" 8'-6" 4'-0" 3'-1" 4'-11" 3'-1" 3'-5"
FXV-0809x-x-x CXVB-x-0809-x
4'-4" 8'-6" 4'-0" 3'-1" 4'-11" 3'-1" 3'-5"
FXV-0812x-x-x CXVB-x-0812-x
4'-4" 8'-6" 4'-0" 5'-3" 4'-11" 5'-3" 3'-5"
FXV-0818x-x-x CXVB-x-0818-x
5'-3" 8'-6" 4'-0" 8'-2" 4'-11" 8'-2" 3'-5"
FXV-1212x-x-x CXVB-x-1212-x
4'-4" 11'-10" 5'-3" 5-'3" 6'-1" 5-'3" 5'-2"
FXV-1218x-x-x CXVB-x-1218-x
5'-3" 11'-10" 5'-3" 8'-2" 6'-1" 8'-2" 5'-2"
W1
H
W2
Figure 6a. Coil Section Lift Figure 6b. Plenum Section Lift
NOTE: For the lower section, see
Figure 1a on page 4.
WARNING: Failure to use lifting
provisions can result in a dropped
load causing severe injury, death,
and/or property damage. Lifts
must be performed by qualified
riggers following BAC published
Rigging Instructions, and generally
accepted lifting practices. The
use of a supplemental safety
sling may also be required if the
lift circumstances warrant its
use, as determined by the rigging
contractor.