Step 9 Set the pump run-over time after heating operation has ended? Yes: → Step 10
No:
→ Step 11
Step 10 Lower: Decrease the target pump run-over time after the end of heating operation with the "
c" button.
The minimum setting is
[f/\/0| = 0 minutes. The factory default setting is 5 minutes.
Higher: Increase the target pump run-over time after the end of heating operation with the "
d" button.
The minimum setting is
[f/1/d| = 24 hours.
Step 11 Press the "
e" button.
Step 12
[c/\1] Display setting: required DHW mode position (on/off).
See also section 28 "Display settings", page 21.
Set the third parameter as soon as the display shows
[c/\/1|.
Step 13 Set the DHW mode status? Yes:
→ Step 14
No:
→ Step 15
Step 14 Set the DHW mode On or Off with the "
c" or "d" buttons. [c/\/1| is "On", [c/\/0| is "Off".
Note! If
[c/\/0| is set, the frost protection for the internal or external hot water tank heater is switched off.
Step 15 Have at least 5 seconds passed without a button being pressed and/or has the main voltage been interrupted ? Yes:
→ Step 17
No:
→ Step 16
Step 16 Press the "
e" button.
Step 17
[\/7/5| Display reading: Currently measured heating system supply temperature in °F.
See also section 27 "Display readings", page 21.
Any adjustments that you have made have been confirmed.
→ Step 1