Loosen both mounting screws [1].
Remove the heat exchanger.
Install the new heat exchanger and all other parts in reverse
order.
Fill and purge the heating system, see section 78.
Open the gas stop valve as indicated in section 81.
Close the boiler door and install the casing of the pump group
in reverse order of removal.
Switch on the power supply to the heating system, see
section 79.
section 130 Replacing the UBA 3
HDANGER OF FATAL ACCIDENT
due to electric shock!
Switch off the power supply to the heating system, see
section 72.
Open the boiler door as instructed in section 73.
Remove the cover from the connection tray, see section 114.
Remove the UBA 3 as instructed in section 82.
Install the new UBA 3 in reverse order of removal.
Install the lid on the connection tray in reverse order.
Close the boiler door as instructed in section 77.
Switch on the power supply to the heating system, see
section 79.