Actions 7
Logamax plus GB162-80 kW/100 kW - Subject to modifications resulting from technical improvements!
73
Remove the cap from the measuring nipple of the combus-
tion air supply.
Pull the plug of the flue gas sensor upwards.
Set the multimeter to "Measure resistance" [1].
Check the electrical resistance of the flue gas sensor by mea-
suring it [2].
Check the flue gas temperatures by measuring them in the
flue gas measuring nipple, see section 1, [16].
Compare the resistance values measured and flue gas tem-
peratures measured, to the values in section 134.
Replace the flue gas sensor if the reading fluctuates by more
than 10 % with respect to the reference value (e.g. infinitely
high resistance in the event of a line break or resistance of
0 Ω in the case of a short circuit).
Attach the plug of the flue gas sensor in reverse order.
Install the cap on the measuring nipple of the combustion air
supply.
Close the boiler door in reverse order.
Switch on the power supply to the heating system, see
section 79.
section 98 Checking the flue gas sensor;
cable
HDANGER OF FATAL ACCIDENT
due to electric shock!
Switch off the power supply to the heating system, see
section 72.
Open the boiler door as instructed in section 73.
Remove the UBA 3 as instructed in section 82.
Remove the cover from the connection tray, see section 114.
Disconnect the plug of the flue gas sensor as instructed in
section 97.
Set the multimeter to "Measure resistance" [1].
Check the safety sensor cable for breaks. The electrical
resistance measured separately for every wire must be
approx. 0
Ω [2]. Measure between the plug and the black
contacts (low-voltage connector pins 65 and 66) on the
UBA 3 mounting base [3].
Check the flue gas sensor cable for internal short circuiting.
The electrical resistance, measured between two random
wires, must be infinite.
Measure the electrical resistance over the flue gas sensor
cable to ground. The electrical resistance must be infinite for
every individual wire.
Attach the plug of the flue gas sensor in reverse order.
Install the lid on the connection tray in reverse order.
Install the UBA 3 in reverse order of removal.
Close the boiler door as instructed in section 73.
Switch on the power supply to the heating system, see
section 79.
1
2
3
81-pin low-voltage connector
16-pin high-voltage connector