POCKET REFERENCE GUIDE 26
Complex Concrete Volume
You’re going to pour an odd-shaped patio
4-1/2 Inches deep with the dimensions
shown below. First, calculate the total Area
(by dividing the drawing into three individual
rectangles) and then determine the total
Yards of concrete required for this job.
A
B
C
27’ 0”
38’ 2”
8’ 6”
9’ 0”
4’ 2”
9’ 6”
Dgm-CCV-103