CL-6
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - -
CUT ALONG DOTTED LINE CUT ALONG DOTTED LINE
SETPOINTS
Fans Setpoints
Set the Bldg Static Press set point (if equipped) to match the design building static pressure from the pre-startup
checklist
Set the Supply Fan Mod DPT set point (if equipped) to match the design duct static pressure from the pre-startup
checklist
Set the Supply Fan Mod AMS set point (if equipped) to match the design supply fan airflow from the pre-startup
checklist
Set the Exhaust Fan Mod AMS set point (if equipped) to match the design exhaust fan airflow from the pre-startup
checklist
ECW Setpoints (if equipped)
Set the ECW defrost set point to match the WExAT from the pre-startup checklist
Cooling 1 Setpoints
Set the Clg #1 enable set point to match the cooling 1 enable above point from the pre-startup checklist
Set the Clg #1 Mod DXLAT set point to match the design cooling coil leaving air temperature from the pre-startup
checklist
Set the Cooling SAT set point to match the design cooling supply air temp from the pre-startup checklist
Cooling 2 Setpoints (if equipped)
Set the Clg #2 enable set point to match the cooling 2 enable above point from the pre-startup checklist
Dehum Setpoints
Set the Dehum enable set point to match the dehum enable above point from the pre-startup checklist
Set the Dehum SAT set point to the dehum design supply air temperature from the pre-startup checklist
Heating Setpoints (if equipped)
Set the heating enable set point to match the dehum enable above point from the pre-startup checklist
Set the heating SAT set point to the heating design supply air temp from the pre-startup checklist
Limits/Safety SP
Adjust the cooling, dehumidification low limits and the heating high limits as necessary
Adjust the compressor 1 and 2 disable setpoints as needed
Unoccupied Setpoints (if equipped with NSB ETO only)
Adjust the cooling and heating ZAT setpoints and dehum ZRH setpoints as indicated on the pre-startup checklist
Unit Control Configuration SAT Reset
Parameter Configuration Parameter Configuration
Zone Sensor Type ZAT Ratio
ZS Button Override SAT Ratio
ZS Set Point Adjust Max Change
ZS Adjust +/- Cooling ZAT
Night Setback Heating ZAT
Misc. Options A
Misc. Options B DPT Summary
Parameter Configuration
Manual Override SF DPT Min
Parameter Output Percent SF DPT Max
Supply Fan Building DPT Min
Exhaust Fan Building DPT Max
EC Wheel
Reheat
Heating