50VR-K: Installation Instructions
Manufacturer reserves the right to change, at any time, specifications and designs without notice and without obligations.
8
paid to excessive wear at hoist hooking points and  load support areas.
Materials showing any kind of wear in these areas must not be used and
should be discarded.
1. Leave  top  shipping  skid  on  the  unit  for  use  as  a  spreader  bar  to
prevent the rigging straps from damaging the unit. If the skid is not
available, use a spreader bar of sufficient length to protect the unit
from damage.
Rigging/Lifting of Unit (See Fig. 5)
1. Lifting holes are provided in base rails as shown.
2. Attach shackles, clevis pins, and straps to the base rails of the unit.
Be  sure  materials  are  rated  to  hold  the  weight  of  the  unit  (See
Fig. 5).
3. Attach  a  clevis  of  sufficient  strength  in  the  middle  of  the  straps.
Adjust  the  clevis  location  to  ensure  unit  is  lifted  level  with  the
ground.
After the unit is placed on the roof curb or mounting pad, remove the top
skid. 
A07926
Fig. 7 – Slab Mounting Detail
Step 6 – Connect Condensate Drain
NOTE:  When installing condensate drain connection be sure to comply
with local codes and restrictions.
This  unit  disposes  of  condensate  water  through  a  3/4  in.  NPT  fitting
which exits through the base on the evaporator coil access side. See 
Fig. 2 and Fig. 3 for location.
Condensate  water  can  be  drained  directly  onto  the  roof  in  rooftop
installations  (where  permitted)  or  onto  a  gravel  apron  in  ground level
installations.  Install  a  field-supplied  2-in.  (51  mm)  condensate  trap  at
end of condensate connection to ensure proper drainage. Make sure that
the outlet of the trap is at least 1 in. (25 mm) lower than the drain pan
condensate connection to prevent the pan from overflowing (See Fig. 8).
When using a gravel apron, make sure it slopes away from the unit.
Connect a drain tube using a minimum of 3/4 -in. PVC or 3/4 -in. copper
pipe (all field-supplied) at the outlet end of the 2-in. (51 mm) trap. Do
not undersize the tube. Pitch the drain tube downward  at  a  slope of  at
least 1-in. (25 mm) for every 10 ft (3.1 m) of horizontal run. Be sure to
check the drain tube for leaks. Prime trap at the beginning of the cooling
season start-up.
A09052
Fig. 8 – Condensate Trap
Step 7 – Install Duct Connections
The  design  and  installation  of  the  duct  system  must  be  in accordance
with the standards of the NFPA for installation of non-residence type air
conditioning  and  ventilating  systems,  NFPA  90A  or  residence  type,
NFPA 90B and/or local codes and ordinances.
Select  and  size  ductwork,  supply-air  registers,  and  return  air  grilles
according  to  ASHRAE  (American  Society  of  Heating,  Refrigeration,
and Air  Conditioning  Engineers)  recommendations. The  unit  has  duct
flanges on the supply- and return-air openings on the side of the unit.
When designing and installing ductwork, consider the following:
1. All units should have field-supplied filters or accessory filter rack
installed in the return-air side of the unit. Recommended sizes for
filters are shown in Table 1.
2. Avoid abrupt duct size increases and reductions. Abrupt change in
duct size adversely affects air performance.
IMPORTANT:  Use flexible connectors between ductwork and unit to
prevent  transmission  of  vibration.  Use  suitable  gaskets  to  ensure
weather-tight  and  airtight  seal.  When  electric  heat  is  installed,  use
fireproof  canvas  (or  similar heat  resistant material)  connector  between
ductwork and unit discharge connection. If flexible duct is used, insert a
sheet  metal  sleeve  inside  duct. Heat resistant  duct  connector (or  sheet
metal sleeve) must extend 24-in. (610 mm) from electric heater element. 
3. Size  ductwork  for  cooling  air  quantity  (cfm).  The  minimum  air
quantity  for  proper  electric  heater  operation  is  listed  in  Table 2.
Heater  limit  switches  may  trip  at  air  quantities  below  those
recommended.
4. Seal,  insulate,  and  weatherproof  all  external  ductwork.  Seal,
insulate  and  cover  with  a  vapor  barrier  all  ductwork  passing
through  conditioned  spaces.  Follow  latest  Sheet  Metal  and  Air
Conditioning  Contractors  National  Association  (SMACNA)  and
Air  Conditioning  Contractors  Association  (ACCA)  minimum
installation  standards  for  residential  heating  and  air  conditioning
systems.
5. Secure  all  ducts  to  building  structure.  Flash,  weatherproof,  and
vibration-isolate  duct  openings  in  wall  or  roof  according  to  good
construction practices.
WARNING
!
UNIT FALLING HAZARD
Failure to follow this warning could result in personal injury or death.
Never stand beneath rigged units or lift over people.
WARNING
!
PROPERTY DAMAGE HAZARD
Failure to follow this warning could result in personal injury. 
When straps  are taut, the  clevis should be  a minimum of  36 in. (914
mm) above the unit top cover.
WARNING
!
UNIT FALLING HAZARD
Failure to follow this warning could result in personal injury or death.
Large base units must be secured to common curb before allowing full
weight of unit to rest on curb. Install screws through curb into unit base
rails while rigging crane is still supporting unit.
OPTIONAL
RETURN
AIR
OPENING
OPTIONAL
SUPPLY
AIR
OPENING
EVAP. COIL COND. COIL
ß
(50.8mm)
TRAP
OUTLET
1-in. (25 mm) min.
2-in. (51 mm) min.