PG96MSA: Installation, Start-up, Operating and Service and Maintenance Instructions
Manufacturer reserves the right to change, at any time, specifications and designs without notice and without obligations.
22
Location Relative to Cooling Equipment
The cooling coil must be installed parallel with, or on the downstream
side  of  the  unit  to  avoid  condensation  in  the  heat  exchangers.  When
installed parallel with the furnace,  dampers or other flow control must
prevent  chilled  air  from  entering  the  furnace.  If  the  dampers  are
manually  operated,  they  must  be  equipped  with  means  to  prevent
operation of either unit unless the damper is in the full-heat or full-cool
position.
Platform Furnace Support
Construct  working  platform  at  location  where  all  required  furnace
clearances are met. See Table 2 and Fig. 26. For furnaces with 1-in. (25
mm)  clearance  requirement  on  side,  set  furnace  on  non-combustible
blocks, bricks or angle iron. For crawlspace installations, if the furnace
is  not  suspended  from  the  floor  joists,  the  ground  underneath  furnace
must be level and the furnace set on blocks or bricks.
Suspended Furnace Support 
The  furnace  must  be  supported  under  the  entire  length  of  the  furnace
with  threaded  rod  and  angle  iron.  See  Fig. 27.  Secure  angle  iron  to
bottom of furnace as shown. 
Roll-Out Protection 
Provide a minimum 12-in. x 22-in. (305 x 559 mm) piece of sheet metal
for flame roll-out protection in front of burner area for furnaces closer
than 12-in. (305 mm) above the combustible deck or suspended furnaces
closer  than  12-in.  (305  mm)  to  joists.  The  sheet  metal  MUST  extend
underneath the furnace casing by 1-in. (25 mm) with the door removed.
The bottom closure panel on furnaces of widths 17-1/2-in. (445 mm) and
larger may be used for flame roll-out protection when bottom of furnace
is  used for  return  air connection. See  Fig. 26  for proper orientation  of
roll-out shield.
AIR DUCTS
General Requirements 
The  duct  system  should  be  designed  and  sized  according  to  accepted
national  standards  such  as  those  published  by:  Air  Conditioning
Contractors  Association  (ACCA  Manual  D),  Sheet  Metal  and  Air
Conditioning  Contractors  National  Association  (SMACNA)  or
American  Society  of  Heating,  Refrigerating  and  Air  Conditioning
Engineers  (ASHRAE)  or  consult  The Air  Systems  Design  Guidelines
reference tables  available from  your local distributor. The duct  system
should be sized to handle the required system design CFM at the design
external  static  pressure.  The  furnace  airflow  rates  are  provided  in
Table 18-Air Delivery-CFM (with filter). When a furnace is installed so
that the supply ducts carry air circulated by the furnace to areas outside
the space containing the furnace, the return air shall also be handled by
duct(s)  sealed  to  the  furnace casing  and  terminating  outside  the  space
containing the furnace. 
Secure ductwork with proper fasteners for type of ductwork used. Seal
supply- and return-duct connections to furnace with code approved tape
or duct sealer.
NOTE:    Flexible  connections  should  be  used  between  ductwork  and
furnace to prevent transmission of vibration. 
Ductwork  passing through  unconditioned  space  should  be insulated  to
enhance  system  performance.  When  air  conditioning  is  used,  a  vapor
barrier is recommended. 
Maintain  a  1-in.  (25  mm)  clearance  from  combustible  materials  to
supply air ductwork for a distance of 36-in. (914 mm) horizontally from
the furnace. See NFPA 90B or local code for further requirements.
Return Duct Sizing
Refer to the Filter Selection and Duct Sizing section for information on
the proper selection of filter sizes and the associated ductwork and duct
transitions. Improperly designed  filtering systems and  return ductwork
are  the  most  common  causes  of  airflow  and/or  noise  complaints  in
HVAC systems.
Ductwork Acoustical Treatment 
NOTE:  Metal duct systems that do not have a 90 degree elbow and 10
ft. (3 M) of main duct to the first branch take-off may require internal
acoustical  lining. As  an  alternative,  fibrous  ductwork  may  be  used  if
constructed  and  installed  in  accordance  with  the  latest  edition  of
SMACNA construction standard on fibrous glass ducts. Both acoustical
lining and fibrous ductwork shall comply with NFPA 90B as tested by
UL Standard 181 for Class 1 Rigid air ducts. 
NOTE:  For  horizontal applications, the top most  flange may be  bent
past 90° to allow the evaporator coil to hang on the flange temporarily
while the remaining attachment and sealing of the coil are performed. 
GAS PIPING
Gas  piping  must  be  installed  in  accordance  with  national  and  local
codes. Refer to current edition of NFPA 54/ANSI Z223.1 in the U.S.A.
Refer to current edition of NSCNGPIC in Canada.
Installations  must  be  made  in  accordance  with  all  authorities  having
jurisdiction.  If  possible,  the  gas  supply  line  should  be  a  separate  line
running directly from meter to furnace. 
NOTE:  Use  a  back-up  wrench  on  the  inlet  of  the  gas  valve  when
connecting the gas line to the gas valve.
NOTICE
!
Many  states,  provinces  and  localities  are  considering  or  have
implemented  standards  and/or  restrictions  on  duct  sizing  practices,
ductwork  leakage,  and/or  ductwork  thermal,  airflow  and  electrical
efficiencies.  CONSULT  LOCAL  CODE  OFFICIALS  for  ductwork
design and performance requirements in your area.
WARNING
!
FIRE OR EXPLOSION HAZARD
Failure  to  follow  this  warning  could  result  in  personal  injury,  death,
and/or property damage. 
Never purge a gas line into a combustion chamber. Never test for gas
leaks with an open flame. Use a commercially available soap solution
made specifically for the detection of leaks to check all connections. A
fire or explosion may result causing property damage, personal injury
or loss of life.
WARNING
!
FIRE OR EXPLOSION HAZARD
Failure  to  follow  this  warning  could  result  in  personal  injury,  death,
and/or property damage.
Use proper length of pipe to avoid stress on gas control manifold and
gas valve.
WARNING
!
FIRE OR EXPLOSION HAZARD
Gas valve inlet and/or inlet pipe must remain capped until gas supply
line  is  permanently  installed  to  protect  the  valve  from  moisture  and
debris. Also, install a sediment trap in the gas supply piping at the inlet
to the gas valve.