START-UP CHECKLIST FOR 48LC SINGLE PACKAGE ROOFTOP COOLING ONLY
(REMOVE AND STORE IN JOB FILE)
I. PRELIMINARY INFORMATION
MODEL NO ____________________________________________
JOB NAME_____________________________________________
SERIAL NO ____________________________________________
ADDRESS _____________________________________________
START-UP DATE________________________________________
TECHNICIAN NAME __
___________________________________
ADDITIONAL ACCESSORIES
_____________________________________________________________________________________________________
II. PRE-START-UP
Verify that all packaging materials have been removed from unit (Y/N) _____
Verify installation of outdoor air hood (Y/N) _____
Verify installation of flue exhaust and inlet hood (Y/N) _____
Verify that condensate connection is i
nstalled per instructions   (Y/N) _____
Verify that all electrical connections and terminals are tight (Y/N) _____
Verify gas pressure to unit gas valve is within specified range (Y/N) _____
Check gas piping for leaks (Y/N) _____
Check that indoor-air filters are clean and in place (Y/N) _____
Check that outdoor-air inlet screens are in place (Y/N) _____
Verify that unit is level (Y/N) _____
Check fan wh
eels and propeller for location in housing/orifice and verify setscrew is tight (Y/N) _____
Verify that fan sheaves are aligned and belts are properly tensioned (Y/N) _____
Verify that scroll compressors are rotating in the correct direction (Y/N) _____
Verify installation of thermostat (Y/N) _____
Verify that crankcase heaters have been energized for at least 24 hours (Y/N) _____
III. START-UP
ELECTRICAL
Supply Voltage  L1-L2_____________ L2-L3_____________ L3-L1_____________
Compressor Amps 1 L1   _____________ L2   _____________ L3  _____________
Compressor Amps 2 L1   _____________ L2   _____________ L3  _____________
Supply Fan Amps L1   _____________ L2   _____________ L3  _____________
TEMPERATURES
Outdoor-Air Temperature  _____________ °F DB (Dry Bulb)
Return-Air Temperature  _____________ °F DB  _____________ °F Wb (Wet Bulb) 
Cooling Supply Air Tempera
ture  _____________ °F
Gas Heat Air Temperature  _____________ °F
NOTE:  To avoid injury to personnel and damage to equipment or
property when completing the procedures listed in this start-up
checklist, use good judgment, follow safe practices, and adhere
to  the  safety  considerations/information  as  outlined  in  preced-
ing sections of this Installation Instruction document.