Conveyor Setup and Adjustment:
For initial conveyor setup refer back to the layout drawing for approximate dimensions. Once the
BBL is in the final Position then take a chalk line and make a line parallel with the BB filler structure
and align the conveyors off that line. Then maintain the following:
For the initial setup make sure the powered discharge conveyors are at equal heights
(in feed and out feed). Also, they must of equal height to the receiving end of the
gravity roller conveyor.
Maintain a minimum clearance of a 1/2" between the bulk bag filler discharge conveyor
and the 2nd conveyor to be sure you don't influence your scale weighing.
A. Maintenance:
Check Live Chain Roller (LRC) once a year and remove slack in the chains as required.
Check oil levels on gear boxes once a year.
B. Installation and Maintenance of Speed Reducers and Drives
This manual provides information concerning usage, lubrication, and maintenance of the
Speed Reducers. To maximize the life and efficiency of your reducers follow these
instructions on a regular basis.
***************
To determine the ratio and/or the assembly date of the reducer refer to the numbers
stamped on the end of the output shaft.
If properly used, the reducer should require little maintenance except for scheduled
lubrication.
Initial Oil Change: Drain the oil in a new Speed Reducer after approximately 500 hours of
operation and refill with recommended oil from lubrication chart.