| Intelect
®
Mobile 2 - Service Manual 58
8.2.2. Tracker sheet for Intelect Mobile 2 STIM Final Test Procedure
1. Serial Number (S/N) ⎵ ⎵ ⎵ ⎵ ⎵ ⎵ ⎵ ⎵ ⎵ Done
2. Software Version: ⎵⎵.⎵⎵.⎵⎵ Done
Electrotherapy
3. Both LED work and channels run for 15 seconds without pause or any popped error. Pass Fail
4. The display indicates “Electrode fault (0x71020000)”. Pass Fail
5. The electrotherapy program is resumed on CH2. Pass Fail
6. The display indicates “Electrode fault (0x41020000)”. Pass Fail
7. The electrotherapy program is resumed on CH1. Pass Fail
Leakage Current
8. The Voltage DC is between 0mV and 10mV after stabilization. Pass Fail
The Voltage AC is between 1mV and 100 mV after stabilization. Pass Fail
9. The Voltage DC is between 0mV and 10mV after stabilization. Pass Fail
The Voltage AC is between 1mV and 100 mV after stabilization. Pass Fail
10. The Voltage DC is between 0mV and 10mV after stabilization. Pass Fail
The Voltage AC is between 1mV and 100 mV after stabilization. Pass Fail
Battery (test optional)
11. The battery is detected Pass Fail
Visual Check
12. All tests performed are passed and the battery is removed. Pass Fail
Current date (YYYY MM DD): ⎵ ⎵ ⎵ ⎵ /⎵ ⎵ /⎵ ⎵
Operator name: _______________________________________
Operator signature: ____________________________________