- 8 -
Propane Units
NOTE: This step by step procedure is only an outline. Refer to the page(s) indicated
for complete instructions.
PROCEDURE: PAGE
1) Hook up LP bottle(s). 13
2) Turn on gas and adjust regulator. 13
3) Set temperature controller(s). 16
4) Make sure tank outlet, sealing hose, and air cleanout valves are closed. 10-11
5) Open Thermal Regulating Gate and close stack diverter if cabinet 18
heating is required.
6) Ignite burner. 16
7) Allow oil temperature to reach approximately 250º F.
8) Start engine per engine operating instructions. 15
9) Regulate cabinet temperature. 18
10) Start agitation. 19
11) Add material, typically 2-3 biscuits if tank is empty. 19
12) Allow for sufficient melting. 20
13) Start material pump. 20
14) Close Thermal Regulating Gate and open stack diverter. 18
15) Attach sealing wand extension and adjust flow. 20-21
16) Begin sealing procedure. 20-21
17) 10-15 minutes before the end of the work day, return temperature 24
control knobs to zero
Operating Sequence

Table of Contents