Cisco Nexus 93108TC-FX3 - Installing Switch in Two-Post Rack with NXK-ACC-KIT-1 RU

Cisco Nexus 93108TC-FX3
66 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
d) Tighten the 10-32 screws to 20 in-lb (2.26 N·m) or tighten the 12-24 screws to 30 in-lb (3.39 N·m).
Step 5 If you attached a grounding wire to the chassis grounding pad, connect the other end of the wire to the facility ground.
Installing the Switch into a Two-Post Rack Using the
NXK-ACC-KIT-1RU Rack-Mount Kit
To install the switch, you must attach front mounting brackets to the switch and secure the switch to the front
of the rack. Typically, the front of the rack is the side easiest to access for maintenance.
This is not the preferred rack installation method. This method may not be earthquake safe and will not be
NEBS compliant.
Note
You must supply the six 10-32 or 12-24 screws required to mount the rails to the rack.
Note
Before you begin
You have inspected the switch shipment to ensure that you have everything ordered.
Make sure that the switch rack-mount kit includes the following parts:
Front rack-mount brackets (2)
Rear rack-mount brackets (2) (not needed for this procedure)
Slider rails (2) (not needed for this procedure)
M4 x 0.7 x 8-mm Phillips countersink screws (12)
Cisco Nexus 93108TC-FX3 ACI-Mode Switch Hardware Installation Guide
20
Installing the Switch Chassis
Installing the Switch into a Two-Post Rack Using the NXK-ACC-KIT-1RU Rack-Mount Kit