Section 5 — Commissioning Hawk 1000
5-4 Part No. 750-366
Figure 5-5. Verify actuator calibration
5.2 Setting Combustion - Parallel Positioning
When actuators for the currently selected fuel have been calibrated, the <Set Combustion> button will be
available on the Main screen. To begin the procedure, press <Set Combustion> and observe the warning that
follows.
Figure 5-6. Begin combustion setup
Press <I READ THE WARNING - I AM QUALIFIED> to continue. An
additional warning screen will appear, notifying the user that the
boiler Operating Limit Relay will be de-energized during combustion
setup.
Press <Confirm Combustion Setup> to continue.