Pre-Installation Guidelines & Checklist
21
Pre-Installation Checklist
The owner should use the checklist below to prepare for the installation of their pelletizer. It
is the owner’s responsibility to verify all the necessary preparations have been made to the
installation site and meet the specications and guidelines detailed in this publication.
Check o each item in the checklist as pre-installation preparations are completed. Once the
checklist is complete, the owner or responsible party will sign and date the Pre-Installation
Conrmation form and return it to Cold Jet.
Completed Task
The installation site of the pelletizer is indoors, well-ventilated, with sucient
clearances on all sides (including the top).
The installation of the CO
2
supply tank is complete and has been lled by the
owner-selected CO
2
supplier (refer to "Liquid CO
2
Supply System" on page 8).
The supply pipeline has been installed and meets the specications described in
"Liquid CO
2
Supply System" on page 8.
The exhaust pipeline has been installed and meets the specications described
in "Gas CO2 Exhaust System" on page 9.
The electrical connections are in compliance with the regional specications
described in "Electrical Service & Supply" on page 10.
The instrument air or CO
2
gas supply for the pelletizer’s pneumatic system has
been installed and meets the specications described in "Instrument Process Air
Supply" on page 10.
The appropriate type and amount of hydraulic oil is on site and available for use
in the pelletizer’s hydraulic oil tank.
Internet connection for remote technical support.
Pre-Installation Conformation Form
I hereby verify the pre-installation preparations listed above have been completed.
Customer: ___________________________________________________________________________________________
Order: _______________________________________________________________________________________________
Owner/Contact: _____________________________________________________________________________________
Signature ____________________________________________________________________________________________
Date: _________________________________________________________________________________________________
Notes/Remarks to Cold Jet: _________________________________________________________________________
Email the signed form to the to the Cold Jet project lead named on the front page

Table of Contents

Related product manuals