Custers Hydraulica B.V. Venray NL
26 maart 2020 www.custers.nl 23
Fig.46
23: Place both 8-rung frames;
24: Place locking pins between the
frames themselves;
25: Place two leading guardrail frames and
click both diagonal ledgers in place on
the 5
th
rung of the frame in question;
Fig.47
26: Place the platform with hatch (on the
5
th
rung from the top); slide both
blow-away protections under the
rung;
Fig.48
27: Repeat steps 22 - 26 until
the preferred level has been reached;