6.5 Storage
When preparing the pump for long-term storage
at temperatures below the freezing point, ush
the pump with an anti-freeze medium type
monopropylene glycol to prevent internal
corrosion or frost in the pump.
For further information on anti-freeze media,
please contact Danfoss High Pressure Pumps.
Recommended procedure:
1. Disconnect the water supply to the pump.
2. Through the lower bleeding plug, empty
the pump housing of water and close it
again.
3. Connect the pump to a tank containing
anti-freeze additive. Connect a hose to the
inlet port of the pump and via another
hose return the ow from the outlet port to
the tank with antifreeze additives.
Storage temperature:
Min. -40°C to max. +70°C
(Min. -40°F to max. +158°F)
4. Quickly start and stop the pump. Make
sure that the pump does not run dry.
The pump is now protected against
internal corrosion and frost.
Warranty
Danfoss APP pumps are designed for long
operation, low maintenance and reduced
lifecycle costs.
Provided that the pump has been running
according to the Danfoss specications, Danfoss
guarantees 8,000 hours service-free operation,
however, max. 18 months from date of
production.
If Danfoss recommendations concerning
system-design are not followed, it will strongly
inuence the life of the APP pumps.
Other factors that aect pump performance and
lifetime include:
- Insucient ltration
- Insucient bleeding and venting
- Running the pump at speed outside
specications.
- Supplying the pump with water at
temperature higher than recommended.
- Running the pump at inlet pressure outside
specications.
- Running the pump at outlet pressure
outside the specications.
- Wrong direction of rotation.
Maintenance
After 8,000 hours of operation it is strongly
recommended to inspect the pump and change
any worn parts, e.g. pistons and shaft
seal. This is done in order to prevent a potential
breakdown of the pump. If the parts are not
replaced, more frequent inspection is
recommended according to our guidelines.
Pump shutdown:
The APP pumps are made of Duplex/Super
Duplex materials with excellent corrosion
properties. It is, however, always recommended
to ush the pump with freshwater when the
system is shut down.
When stopping the pump for more than 1 day
ush the pump with permeate by rotating the
pump for 10 sec. Flushing through the ashing
valve of the pump without rotating the pump is
not enough for cleaning the inside of the pump.
The pump can be ushed with biocide like the
membranes. The biocide must be compatible
with the materials used in our pump (materials
can be found in the parts list in the Service guide
and Operating manual).
Repair
In case of irregular function of the APP pump,
please contact Danfoss High Pressure Pumps.
7. Service and warranty
Storage:
Storage of pump that have been in operation:
For shorter periods of storage ush the pump
with permeate by rotating the pump for 10 sec.
empty permeate and store.
For long term storage (more than 2 months)
Danfoss recommends servicing the product and
clean any biological growth of the surfaces. Store
the pump without water inside.

Table of Contents

Other manuals for Danfoss APP series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Danfoss APP series and is the answer not in the manual?

Danfoss APP series Specifications

General IconGeneral
BrandDanfoss
ModelAPP series
CategoryWater Pump
LanguageEnglish

Related product manuals