Connection for 230V version with encoder
•Fortheoperatorpowersupplyconnectionfollowtheinstructionsofthebasicversion.
•Openasecondholeintheplasticcoverandapplythesecondprovidedcableclamp(areducedM16).
•Use a 3x0,25mm² LiYY (DEA art. 182021) to be ordered a part) and follow the diagram to correctly connect the encoder to the
control board.
•Use the cable with panduit connector supplied in the kit to connect the previously used cable to the control board, by using the clamp
3 “poli” inside the package.
230V with encoder
M
1(bianco)
2(blu)
3(nero)
ENCODER
}
white
green
brown
CHIUDE
COMUNE
APRE
w
h
i
t
e
b
r
o
w
n
green
 WARNING Maintain the ground conductor at a major length respect the active conductors so that, if the cable exit from its fixing 
housing, the active conductors tighten up as first.
 WARNING  Respect the Phase-Neutral polarity of the tension as explained by the instructions manual of the control panels of 
MAC.
• Re-assembletheplasticcoverensuringthatanycabledonottouchmovingpartsoftheoperator.
 WARNING  while installing, maintain a proper distance between the power cable conductors and the operator.
Program the control board to complete all adjustments. It is now possible to supply a complete installation in compliance with all 
standards required for gate automation. See the instructions provided with the control panel to be connected.
6  UNLOCKING AND MANUAL OPERATION
In the event of malfunctions or simple power failure, release the motor (Pic. 8) and perform the operation manually.
The knowledge of the unlocking device is very important because, in times of emergency, lack of speed in operating this device can 
cause danger.
 WARNING  The efficancy and safety of manual operation of the automation is guaranteed by DEA System only if the installation 
has been installed correctly and with original accessories.
7  START-UP
The start-up phase is very important to ensure maximum security and compliance to regulations, including all the requirements of 
EN 12445 standard which establishes the test methods for testing the automation for gates.
DEA System reminds that all installation, maintenance, cleaning or repair operations on any part of the system must be performed 
exclusively by qualified personnel who must be responsible of all texts requie by the eventual risk;
7.1.  Installation test
The testing operation is essential in order to verify the correct installation of the system. DEA System wants to summarize the proper 
testing of all the automation in 4 easy steps:
●  Make sure that you comply strictly as described in paragraph 2 “WARNINGS SUMMARY”;
●  Test the opening and closing making sure that the movement of the leaf match as expected. We suggest in this regard to perform 
various tests to assess the smoothness of the gate and defects in assembly or adjustment;
●  Ensure that all safety devices connected work properly;
●  Perform the measurement of impact forces in accordance with the standard 12445 to find the setting that ensures compliance with 
the limits set by the standard EN12453.
 WARNING Using spare parts not indicated by DEA System and/or incorrect re-assembly can create a risk to people, animals and 
property and also damage the product. For this reason, always use only the parts indicated by DEA System and scrupulously follow 
all assembly instructions.