3. Commissioning of the Multi-line 2
3.1 Step by step
3.1.1 Step by step
The illustration below indicates the overall steps to be followed in order to carry out a successful commission-
ing of the Multi-line 2 unit.
Step 1 Settings check
Step 2 Governor check
Step 3 AVR check
Step 4 Protections check
Step 5 Adjustment
In addition, the generic troubleshooting in the chapter "Troubleshooting" can be used.
General guidelines for commissioning
4189340703 UK
Commissioning of the Multi-line 2
DEIF A/S Page 7 of 25