If on-site insulation testing is required, make sure:
1. The DC switch is in the “OFF” position.
2.
Place one probe in any DC connectors shown in Figure 3-24 and the other on
the ground.
3.8 On-Site Insulation Test
Figure 3-24: Precautions for on-site insulation test
DC Switch OFF
OFF
ON
DC connectors