Powerbox Pro series User Manual
12
3 Installation and Configuration
3.1 Preparations for installation
Safety Requirement
This system can only be installed by personnel who have been trained in the power-supply
system and have sufficient knowledge of the power system.
The safety regulations and local safety regulations listed below should always be followed during
the installation.
All circuits connected to this power system with an external voltage of less than 48V must
meet the SELV requirements defined in the IEC60950 standard.
If operating within the power system cabinet, make sure the power system is not charged.
Battery devices should also be switched off
Distribution cable wiring should be reasonable and has the protective measures to avoid
touching these cables while operating power equipment.
when installing the battery system, must wear the protective items below:
The isolation gloves Safety goggles Safety shoes
3.1.1 Environmental requirements
Working temperature: -20 ~ +55
Charging temperature range is 0~+55 ,
Discharging temperature range is -20 ~+55
Storage temperature: -10 ~ +35
Relative humidity: 5% ~ 85%RH
Elevation: no more than 4000m
Operating environment: Indoor or outdoor installation, sites avoid the sunlight and no wind,
no conductive dust and corrosive gas.
And the following conditions are met:
Installation location should be away from the sea to avoid brine and high humidity
environment.
The ground for product arrangement shall be flat and level.
There is no flammable explosive materials near to the installation site.
The optimal ambient temperature is 15 ~ 30
Keep away from dust and messy zones