Powerbox Pro series User Manual
16
Step1
System outage
Ensure that the battery is in a shutdown state
Step 2
Mechanical
installation
1. Hanger mounting
2.Equipment installation
Step3
Electrical
installation
1. Connect the ground cable
2 Electrical installation
3.Connect inverter
4.Communication interface connection
3.2.1 Floor installation
When the battery system is placed directly on the ground, a fixed support must be used
to fix the top of the battery box on the wall.
3 Press the marked position with the
electric drill and trepanning 4 holes
with a diameter of 10mm on the wall.
The hole depth shall be greater than
70mm for fitting the expansion bolt of
M6.
1 Use the positioning cardboard
(provided in accessory package)
and mark the screw hole positions
on the wall, as shown in the four
holes on the left.
2 The bottom of board must be
good connection with the ground
level while marking the holes.