Eaton 9395XC UPS 1200kW/1200kVA, 1350kW/1350kVA or 1500kW/1500kVA 164001079—Rev 01 47
Figure 20. UPS Forklift Locations
I/O Section Forklift Location
ISBM/PM Section Forklift Location
8. Proceed to paragraph 4.3 Installing and Connecting the UPS Sections.
44..33 IInnssttaalllliinngg aanndd CCoonnnneeccttiinngg tthhee UUPPSS SSeeccttiioonnss
44..33..11 PPrreeppaarriinngg tthhee UUPPSS SSeeccttiioonnss
NOTE For the following steps, verify that the forklift or pallet jack is rated to handle the weight
of the section (see Table 2 for cabinet weight).
Position the sections as follows:
Use care during installation to protect components mounted on the right side of the I/O section and the inter-
cabinet wiring harnesses attached to the left side ISBM/PM section from damage.
UPS System Installation