3.2.3 Preparation prior to installation
The location of the unit is required to meet the conditions
stated in par. 3.1.2.
1. Remove the packaging and check the contents.
2. Remove the doors of the left- and right-hand panels,
see Figure 3-4.
TIP
The door can only be removed if the panel is in the
'Cable earthed' position. See procedure in
section 4.2.2.
3. Remove the 4 fixing bolts (1) (2 either side), see
Figure 3-5 and then remove the pallet.
4. When positioning the unit check that:
the cable openings in the floor are in the correct
position;
the floor is clean and level;
the unit is not damaged.
5. Slide the unit across the floor to its final location, if
necessary. Apply a lever to the base plinths only. Take
care not to damage the unit.
Figure 3-4: Opening the cable access door
Figure 3-5: Location of fixing bolts
1
1
1