10 Starting up the UPS equipment
To guarantee error-free startup, the following actions must be carried out:
1. Check the line-side fuse then connect the equipment to the power
supply.
2. Switch the UPS on (main switch on the front of the equipment).
3. Wait until the UPS is in on-line mode.
4. Now connect the consumer loads one by one, observing the load
indicator.
If all of the steps have been completed successfully, the UPS will be in on-line
mode and the load indicator will be less than 100%.
5. Now switch the system off (main switch on the front of the equipment).
6. Wait a few seconds (“refresh”).
7. Switch the UPS on again (main switch on the front of the equipment).
The UPS equipment should revert to on-line mode after a few seconds. This
test ensures that the system will also start when the total load is connected.
The equipment can now remain ready for operation in this state.
11 Troubleshooting
Troubleshooting on the UPS equipment may only be performed by authorised
technical personnel.
If the UPS does not work properly, try to resolve the problem by referring to the
following table: