Installation
24
2.8 Checklist for Completed Installation
___ 1. All items unpacked and checked.
___ 2. Proper clearances for service access maintained around equipment.
___ 3. Equipment is level and mounting fasteners are tight.
___ 4. Piping completed to refrigerant loop.
___ 5. All piping connections are tight.
___ 6. Piping routed to prevent chafing and rub-through.
___ 7. Piping has been evacuated and refrigerant charge added (if required).
___ 8. Line voltage to power wiring matches equipment nameplate.
___ 9. Power wiring connections completed, including earth ground.
___ 10. Power line circuit breakers or fuses have proper ratings for equipment installed.
___ 11. Control wiring connections completed.
___ 12. All wiring connections are tight.
___ 13. Foreign materials have been removed from area: in and around all equipment installed
(shipping materials, construction materials, tools, etc.).
___ 14. Fans and blowers rotate freely and in the proper direction.
___ 15. Blank startup sheet has been sent with the evaporator unit and is ready to be completed by
the installer.
Table 21 Electrical data - Quiet-Line models (95°F/35°C) 50Hz
Model #
Nominal
Capacity
Tons
* Electrical
Characteristic
Input Voltage-Phase
220-1 200/230-3 380/415-3
13 1 FLA
19 1.5 FLA
26 2 FLA 12.3 4.8
36 3 FLA 18.0 6.9
41 3.5 FLA 17.3 8.4
66 5 FLA 22.5 12.4
95 8 FLA
* FLA = Full Load Amps