Commissioning TMT162
20 Endress+Hauser
6 Commissioning
6.1 Installation check
Before commissioning the measurement point make sure that all final checks have been carried out:
• Checklist “Installation check”
• "Connection check"
6.2 Switch on the device
Once the power has been connected, the field transmitter is operational.
6.3 Quick Setup
Using the Quick Setup the operator is led through all the most important unit functions, which must
be set up for standard measurement operation of the unit.
Standard setup
Available in ReadWin
®
2000, HART
®
handheld module
DXR275/375 (Symbol
7
), Commuwin II with Matrix address
ReadWin
®
2000
7
/FieldCare CW II-Matrix
Function mode + + V1H1
PV mode + + V1H2
PV unit + + V1H3
Sensor 1
Sensor type + + V3H0
Sensor connection + + V3H1
Measuring unit + + V3H6
Sensor 2
Sensor type + + V4H0
Sensor connection + + V4H1
Measuring unit + + V4H6
Output
PV lower range value + + V1H4
PV upper range value + + V1H5
Safety settings
Fault condition + + V1H8
Ambient alert + + V2H2