Electrical connection Levelflex FMP55 HART
52 Endress+Hauser
7.3 Post-connection check
m Are cables or the device undamaged (visual inspection)?
m Do the cables comply with the requirements?
m Do the cables have adequate strain relief?
m Are all cable glands installed, firmly tightened and correctly sealed?
m Does the supply voltage match the specifications on the transmitter nameplate?
m Is the terminal assignment correct (→ 30)?
m If required: Is the protective earth connected correctly (→ 30)?
m
If supply voltage is present: Is the device ready for operation and do values appear on the display
module?
m Are all housing covers installed and firmly tightened?
m Is the securing clamp tightened correctly?